Discussion: LEAP

All Discussions | All Topics | Topic "Merit Order Electric Modelling"
Login to post new messages or reply to existing messages.
 
Author Message
Agus Cahyono Adi
Subject: Merit Order Electric Modelling   
Posted: 8/25/2004 Viewed: 2543 times |
Merit Order Electric Modelling Agus Cahyono Adi agusadi <a href="mailto:agus@eapo.or.id">agus@eapo.or.id</a>
Dear Charlie,



I wondering, when running Electricity model using dispatching process with merit order. The result when we are using Load Factor seem dosn't consider the merit order setting in the process properties. Where as, by using load curve data the maximum capacity factor couldn't reached even using endogenous capacity.



Are there any detail reference how LEAP model the Merit Order Dispatching Process?



Thank you for your attention and assistance.



Regards



Agus Adi


Topic "Merit Order Electric Modelling"